Voorhees Travel Alert: Kresson Road Construction

kresson road constructionThe Kresson Road Construction Project begins May 2, 2016, and will last approximately four months.

Travelers can expect traffic delays reaching Cooper University Health Care offices on Main Street and Centennial Boulevard in Voorhees, NJ. Please plan accordingly to allow yourself sufficient time to get to your appointments.

  • Construction on Kresson Road in Voorhees will be between Evesham Road to west of Route 73.
  • The project will take 120 days starting Monday, May 2, 2016, and ending in August 2016, depending on weather.
  • Expect work from 7 a.m. to 3:30 p.m., Monday through Friday.
  • Two-way traffic will continue from May through mid-June 2016.
  • Expect a one-way detour from mid-June to mid-July 2016 for paving of Kresson Road.

More information on the Voorhees Township website here.